Search Filter

ROAD CONSTRUCTION NOTICE
Week of October 2, 2023

Please see below for road construction notices in process and upcoming.    

Should you wish to report a pothole, please use our convenient, on-line POTHOLE PORTAL

Recycling Notice: Occasionally, a road closure will prevent a scheduled recycling collection.  Should this occur, please email This email address is being protected from spambots. You need JavaScript enabled to view it.  with your address and they will confirm a makeup date. 

Mayor Hornik announces $35mm 7-year road construction plan as an extension of his existing $10mm road repair initiative.  MORE…

ROAD TO REMAIN OPEN – CONSTRUCTION ADVISORY – POLICE PRESENT

All construction from 7am until 5pm unless stated otherwise

Mockingbird and Peacock Lanes – Monday (10/2) construction crews will be performing roadway paving operations.

Dunn Drive, Melissa Court, and Lee Court - Monday (10/2) through Wednesday (10/4) construction crews will be performing roadway milling paving operations.

Clubhouse Lane, between Coventry Terrace and Murray Hill Terrace - Wednesday (10/4) through Friday (10/6) construction crews will be performing roadway milling paving operations.

 

LLOYD ROAD WATER MAIN REPLACEMENT PROJECT

Police Present – Intermittent Lane Closures

UPDATE - The Marlboro Township Water Utility Division continues improvements to the Water Distribution System to ensure the continued reliable supply of potable water to its customers.  A Project began on April 5, 2023 to replace the water main along Lloyd Road between Route 79 and the Aberdeen Township border.  The project generally consists of full water main replacement including all applicable valves and fire hydrants.  The construction crews will be working on the connections at intersections.  This project is anticipated to last through fall. 

UPCOMING – FUNDED IN PART BY NJDOT GRANT

 

Ryan Road (UPDATE) – The Ryan Road program bid has been awarded and will be on the agenda to be authorized by the Township Council at the meeting to be held October 19.  (MORE).  This road project will be completed, in part, with a NJ DOT Municipal Aid Program for in the amount of $251,900. 

The scheduled time frame for roadwork is weather-dependent, and every effort will be made to minimize any inconvenience to residents during this time.  Please call Marlboro Traffic and Safety at 732-536-0304 with further inquiries.